On June 16, 2011 Construction Investment Joint Stock Company No. 5 held the commencement of construction of package No. 5: “Construction of factories, dynamic zones, auxiliary and infrastructure” project Da Nang Dairy Factory ” at Hoa Khanh Industrial Park – City. Da Nang, invested by Vietnam Dairy Products Joint Stock Company (Vinamilk). Project value: 3,160,828 USD, construction time 250 days.

To ensure the progress committed to the investor, in the first days, the Company gathered at the construction site technical staffs with many years of experience as well as a team of highly skilled workers with many technical equipment. New equipment to carry out the work.

This is the 5th project that the company has won the bid for, invested by Vietnam Dairy Products Joint Stock Company.